Green Energy Corridor scheme-II
November 23 , 2024
4 days
88
- The National Transmission plan report was released by the Central Electricity Authority (CEA).
- Transmission system at a cost of ₹719.76 crore is planned for Tamil Nadu under the Green Energy Corridor-II (GEC-II) Scheme.
- Under the scheme, about 19 gigawatts (GW) of the renewable energy capacity is planned to be integrated into the transmission system within States.
- For Tamil Nadu, 4,000 MW of renewable energy capacity addition is envisaged.
- It is targeting a transmission line of 624 circuit kilometres (ckm) and 2,200 Sub-stations (MVA).
- Under the Green Energy Corridor-I (GEC-I) Scheme, about 23 GW of renewable capacity was planned to be integrated to the intra-State network.
- About 18.72 GW have been commissioned (till 31 March, 2024).
Post Views:
88